7. RECOMMENDATIONS FOR FUTURE SITE
EVALUATION PROGRAMS
7.1 TOWER AND EQUIPMENT CONFIGURATIONS
Based on our experiences in the Meteorological Validation
Program, we offer the following recommendations for equipment
installations at sites being evaluated for large wind turbine
utilization:
- If possible, measurements at least as high as the hub of the
machine should be obtained. One, and preferably two additional
levels, should be installed to allow data to be extrapolated to
the hub height or higher, and to provide important information on
the vertical shear characteristics at the site.
- Nevertheless, it is preferable to keep the height of the tower
below 62 m (200 ft), since the Federal Aviation Administration
(FAA) requires a beacon light on towers higher than this (in some
cases, a beacon light would be required even for shorter towers,
and after the turbine is installed a beacon light might be
required at the height of the blade tip). The operation of the
beacon lights requires ac power and, at least early in the site
evaluation stage, electrical power may not be available at the
site.
- The climatological conditions at the site should be considered
before ordering equipment. If severe gustiness or icing is
possible, more rugged sensors should be utilized (at the expense
of the capability to obtain long-term, high-resolution turbulence
data). If severe moisture could be a problem, special instrument
enclosures and circuitry designs should be considered to assure
that the data logging equipment stays absolutely dry and
operational. If severe cold is a problem, the data logging
equipment should be placed in a heated enclosure, or some type of
resistance heat element installed in the enclosure.
- It is preferable to install towers at locations where icing
conditions are minimized. However, if icing is a problem at a
chosen location, special care should be taken in the tower installation
to ensure
that a heavy load of ice will not buckle the tower or cause a guy
wire to break loose. In the MVP, some problems were encountered
with standard guy grips at sites where severe icing was
experienced. Water would work its way inside the grip during
thaws, and then expand and loosen the grip during refreezing. The
grip should be designed to eliminate this problem.
- Although it is preferable to power the data loggers with ac
power, in many cases none will be available. Some type of
reliable onsite battery charging system should be a part of the
equipment, such as solar cells or windchargers. (These were not
available in this program, but would have simplified the utility
personnel's weekly procedures.)
- Some type of remote data transfer system is recommended (using
telephone lines, communications satellites, or telemetry) and a
system to automatically incorporate the data into a computer data
base is recommended. This will greatly improve data recovery rates
and allow for more efficient site maintenance procedures.
Nevertheless, it is still recommended that local people be
utilized as much as possible to maintain a visual check on the
equipment. An onsite data logger should still be used as a backup
recording system.
7.2 SAMPLING AND DATA PROCESSING PROCEDURES
In Section 5 we discussed an expanded data
collection program
at the turbine installation sites. One feature of this program is
to provide better guidelines on data collection procedures at
sites where turbines could be installed, so that the data base
more closely resembles the turbine operating logic. Detailed
analysis of data collected at these sites has begun, and at this
time we can offer the following preliminary recommendations on
data collection procedures (see also
Renne and Corotis 1981,
Corotis 1982):
- The two-minute instantaneous samples provide an adequate
sampling scheme for climatological purposes. However, they do
not resemble the logic used by the wind turbines for
start-up/shut-down procedures.
- For machine performance evaluation, some type of data averaging
is appropriate. A suggested sampling rate of once every 10
minutes is made, with the following pieces of information
recorded:
- a 1-second average wind speed
- a 15-second average wind speed (experience has shown that this
correlates well with turbine performance)
- a 1-minute average wind speed (correlating with the sampling
procedure followed at routine National Weather Service Stations)
- a 10-minute average wind speed (for machine operating procedures)
- the variance of all 15-second averages within the 10-minute
average
- maximum wind gust during the 10-minute sampling period.
REFERENCES
TABLE OF CONTENTS
Operated for the U.S. Department of Energy by Battelle Memorial Institute
Return to RReDC home page ( http://rredc.nrel)